At 3:26pm of May 31st, we had a successful test of our first toilet.
Boyd tells me that both men's and women's rooms are now operational,
with only the unrinal awaiting being installed.
We are also waiting on the kitchen sink to go in.
The sheet rocking is now done as far as initial instillation (save
two
pieces inside the storage room awaiting installation of lighting for
the kitchen counter). We still have mudding to do on about 1/2 of the
sheet rock and the painting as well.
Some cleanup will need to be done, and the carpet and kitchen area
will need to be installed. We are also nearing the point where the
roll off roof observatory structure will go up.
The guys are tough and have been banging away on this project almost
every Saturday since the start of the year and everyone should be
congratulated on the amount and quality of the work done for weekend
warriors and because of their dedication.
Jeff