I see that we have a number of new members to this discussion group now. I would like to say hello to everyone, and post a short update on what is going on at...
This Friday night I will be introducing a proposed set of use policies for the CRO. They will not go into effect until everyone has had a chance to look them...
Hello group, I am the VP of another astronomy club in S. Florida and am up here attending FAA training. I was looking for a group to join for the 2 months I am...
Sorry about that Don. I didn't see your pending note until Monday. My answer to your inquiry about attending would have been "Certainly. Visiting astronomers...
First of all Happy Moon Landing Anniversary to everyone! Quite a bit has been happening in terms of CRO Development that has not been posted here yet. Most of...
Okay folks, it's finally starting to happen. This past week we were informed by the windmill company that we have nothing to be concerned about as far them...
Over the past two weekends, our dedicated group of weekend warriors have done a great job in creating the foundation of the building. The footings have been...
Yesterday a crew of 15 volunteers came out and took care of the main cement pour. The main building, the southern roll off roof observatory, and 3 - 9' x 9'...
The building now has the steel frame erected and awaits the addition of the wall and roof panels as well as the insulation. This should all go up next Saturday...
I'll be there with BBQ bells on! Christian ... From: Jeff Tibb <JeffTibb@...> To: CheddarRanchObservatory@yahoogroups.com Sent: Sunday, February 10,...
All four walls are now erect and insulated. Two of the three doors have been installed and there is a crew putting on the roof today. Hopefully that can be...
Moving and grooving... The outer shell has been finshed for a couple of weeks now and we are moving on the inside. Today the inside walls were all framed, and...
Work continues almost every weekend now on the interior as we work towards being ready for our May 31st opening date. A small crew of five come out this...
Continual steady progress -- This Saturday morning we installed the septic system. Tank and lateral lines were installed. The indoor wiring is just about...
At 3:26pm of May 31st, we had a successful test of our first toilet. Boyd tells me that both men's and women's rooms are now operational, with only the unrinal...
We are ready to go on the 26th. The roll off roof observatory is now operational and the 12" Cassagrain scope from OU is now in stalled. We have some old...
Planning on being there. Still have to work so I may be late but I will be with open eyes...and maybe a few flyers for our next "in-town" celebration. All...
Well, we did it! The CRO is now officially open. I counted about 120 people at the event. The weather even cooperated, and everyone had a great time. Thanks to...
Weather permitting, members of the Oklahoma City Astronomy Club will be at the CRO to welcome guests form the genral public to tour our facility and look...
Sounds cool...I think I am off that weekend but with Okie-Tex vacation my schedule may change. All I can say as a first timer is WOW. Too bad the weather...
I am wondering,do we have an overall manifest of what we put in to the building on a hourly,daily,weekly,monthly,and yearly basis.I feel than instaed of...
I was wondering if anyone have put on paper any perfered types of telescopes to eventually buy for any additional additions to the main building?Does anyone...
Chris, I would hardly call us 'beyond broke'. We have enough money to operate this year and to do some more improvements, and to keep some money in the bank...
Chris, Travvy posted a list of general jobs for this spring/summer on the club's discussion board: http://www.okcastroclub.com/phpBB2/viewtopic.php?t=1662 Jeff...