Hi, We're experimenting with a live text stream of Sanjiv's event through Facebook. So, even if you are out of Chennai, you can still participate. Here is how:...
961
Mukkesh Kumar
mukesh_8
Sep 1, 2010 11:38 am
How to do size estimate in scrum for product backlog items ? Thanks Mukkesh Sent from my iPhone...
962
Siddharta Govindaraj
photon_ent
Sep 2, 2010 5:01 am
Okay, looks like the live stream didn't work too well. Facebook only showed _some_ of the status updates, not all, and different people saw different updates,...
963
Divakar Singh
dpsmails
Sep 2, 2010 9:12 am
What is the level of the items to be estimated: Theme/Epic/User Story? Best Regards, Divakar ... From: Mukkesh Kumar <mukesh_8@...> Subject:...
964
pankaj215
Sep 12, 2010 3:58 pm
Please suggest on team structure recommendations in Distributed Agile Model where team is located at more than one place. On the same line, what is Agile...
965
pankaj215
Sep 12, 2010 4:04 pm
Mike Cohn has presented some great content on Agile estimation in cluding his book "Agile estimation and Planning". This is good link to start with. Good Luck ...
966
Siddharta Govindaraj
photon_ent
Sep 12, 2010 4:15 pm
... The best structure is to have separate cross-functional teams at each location, each with its own scrum master and product owner. What you definitely don't...
967
Rajeev Agarwal
rajeev.agarwal
Sep 12, 2010 4:52 pm
To add to that, its good to have one of the team member as the scrum master for every team. If you have dedicated scrum masters (only doing the scrum master...
968
pankaj215
Sep 12, 2010 5:01 pm
Thanks Rajeev & Sid These are welcome suggestions and really appreciate quick responses. I joined this forum today itself and liked the responsiveness and...
969
Jesse Fewell
JesseFewell
Sep 12, 2010 6:50 pm
I agree with Sid, and offer one more bit of advice... If you are just starting out with large distributed organization, another best-practice is to start with...
970
pankaj215
Sep 13, 2010 2:13 am
Thanks, In case where co-location is not possible, in typical global model. What are the recommendations, some of these I can think of… ~ Working for...
971
Siddharta Govindaraj
photon_ent
Sep 13, 2010 3:02 am
... Well, there are many adaptations for distributed teams. Here is a list - http://bit.ly/91KsSq Try each and see which ones work for you. It varies from team...
972
Vikrama Dhiman
vickydhiman
Sep 13, 2010 12:45 pm
I think it is important to understand that Scrum was designed keeping some things as a given. One of them was a co-located team. It can be sometimes...
973
pankaj215
Sep 13, 2010 2:19 pm
Thanks All, Great responses!!!...
974
monica_yap
Sep 17, 2010 7:42 pm
There are many good suggestions on this thread. I think Scrum is better for distributed development vs. other methods, since it is driven by frequent inspect...
975
pankaj215
Sep 21, 2010 12:43 pm
Thanks Monika!!! I saw your white paper on distributed agile model, very interesting!!! Great work!!!...
976
Dushy Singh
dushysingh25
Sep 23, 2010 3:31 pm
Dear All, Â Recently after completing some sprints, we discovered a new metric called as Achieved DONE ness defined as ratio of the sum of the story points of...
977
Manoj Vadakkan
manojvp100
Sep 23, 2010 4:00 pm
Dushy, These are the questions pops out in my head when I read your note is this.. Why is there a discrepancy between product owner’s definition of...
978
Jesse Fewell
JesseFewell
Sep 24, 2010 12:55 am
... I understand what you are trying to accomplish here, and I agree. Namely, you want a metric that reveals the cost and error of a team over-committing, in...
979
Pushkar M. Tamboli
pushkar_tamboli
Sep 29, 2010 4:51 am
Jesse, Thats a good index. Actually the problem i see with you team is they are doing *done* part only and not the *done done* part. Done = Business done...
980
Siddharta Govindaraj
photon_ent
Sep 29, 2010 5:27 am
IMHO, I dont get the point of tracking this metric. Getting a story done should be a hard stop. If its not engineering done, then it shouldn't even go to the...
981
Divakar Singh
dpsmails
Sep 29, 2010 5:30 am
+1 to Siddharta. Making Scrum very complex and metrics based can only help in making you less Agile. Best Regards, Divakar ... From: Siddharta Govindaraj...
982
Vikrama Dhiman
vickydhiman
Sep 29, 2010 6:56 am
+1. I also feel "speed" is context dependent and might not be an important criteria in some situations. Agile principles will, ideally speed up things but...
983
Jesse Fewell
JesseFewell
Sep 29, 2010 7:09 am
Each team should derive the measurements *they* need, in order to understand how well they are doing. Siddharta is right in that the team should view the...
984
Madhur Kathuria
madhurgenius
Oct 12, 2010 6:39 am
... From: Organization Committee <org@...> Date: Mon, Oct 11, 2010 at 2:39 PM Subject: Gentle Reminder: Registrations Open for Agile Tour...
985
poojawandile
Oct 20, 2010 12:49 pm
Hi, I am struggling with velocity measurement for an onsite-offshore model. A user story is jointly owned by onsite as well as offshore team members and hence...
986
Siddharta Govindaraj
photon_ent
Oct 20, 2010 1:46 pm
... Hi Pooja, What do you mean by owning the story? Is the offshore team developing only parts of the story, or the whole thing? Also, why does the onsite team...
987
Ravi Rajamiyer
ravirajamiyer
Oct 20, 2010 2:20 pm
Hello Pooja, This relates closely to my current situation as a Scrum Master for a scaled Scrum project involving two offshore scrum teams with on-site team...
988
nanda lankalapalli
nlankalapalli
Oct 20, 2010 2:28 pm
IMO, velocity should only be used for planning purposes. If it is used to measure team's performance, that could lead to unwanted side effects. I didn't...
989
Divakar Singh
dpsmails
Oct 20, 2010 3:57 pm
Pooja, The best situation for distributed team is when they are not working on same user stories at a time. Though there are tools and a few methods which aid...