when to use planning poker ?   Message List  
Reply | Forward Message #454 of 539 |
Re: [ScrumChina] when to use planning poker ?

pre-planning meeting is held for every iteration, 2-3 days before. Normally Monday is planning meeting, then Wednesday in previous week is selected for this pre-planning meeting.

Originally we don't have this meeting, and the whole team discuss with PO to clarify the requirement, it is waste.

Therefore in this pre-planning meeting, 2-3 people who foresee will work on this tasks with join this discussion, and bring feedback to the team. It save a lot of time practically. And this is not official meeting, normally people will stay up to discuss.

rgs/larry

On Mon, Jul 6, 2009 at 12:41 PM, Bas Vodde <basv@...> wrote:



Hi Larry,



> In the pre-planning meeting, we notice 2-3 people discuss with PO
> are good enough, then no planning poker normally needed.
>

I suppose your "pre-planning meeting" is similar as a backlog
refinement (or grooming) meeting? (meaning looking abour 2-3 sprints
ahead).

Why did you 'optimize' it to have only 2-3 people, this will lead to
another hand-off to the rest of the team later?

Bas

>
>
> .. so when we shall use planning poker.
>
> I want to check whether we missed some nice practice for planning
> poker.
>
> rgs/larry
> --
>
> True software development embraces consistent inconsistency.
>
>



--

True software development embraces consistent inconsistency.


Mon Jul 6, 2009 7:12 am

larrycaiyu
Offline Offline
Send Email Send Email

Forward
Message #454 of 539 |
Expand Messages Author Sort by Date

Hi: I start to confuse when to use planning poker. Originally we use planning poker in scrum planning meeting 1, and notice it cost a lot of time, then we...
Larry Cai
larrycaiyu
Offline Send Email
Jul 6, 2009
1:50 am

Based on our practice the planning poker helps to find out the gap between different members in understanding of requirement as well as design. Even though...
neil_feng
Offline Send Email
Jul 6, 2009
2:00 am

Use planning poker to estimate user stories / feature items (whatever you call it) in Product Backlog Grooming session. - Xu Yi...
kaverjody
Offline Send Email
Jul 6, 2009
4:06 am

Hi Larry, ... I suppose your "pre-planning meeting" is similar as a backlog refinement (or grooming) meeting? (meaning looking abour 2-3 sprints ahead). Why...
Bas Vodde
basvodde
Offline Send Email
Jul 6, 2009
4:42 am

pre-planning meeting is held for every iteration, 2-3 days before. Normally Monday is planning meeting, then Wednesday in previous week is selected for this...
Larry Cai
larrycaiyu
Offline Send Email
Jul 6, 2009
7:13 am

We use planning poker when we do backlog planning/grooming, and also when we do task breakdown for a sprint. Some of our projects are "fixed" scope (we know...
vernonstinebaker
vernonstineb...
Offline Send Email
Jul 6, 2009
8:49 am