CMMI Experts: I have been following this group for some time and decided to post a question seeking some help. My question is: What is a measurement...
Good day, A measurement repository is a repository (or storage) used to collect and make available measurement data. Such repository contains or references...
I might add one point to Christof's excellent post - assumptions and rationale for estimates and other significant events affecting the project should be...
Hi GS, As you have found, there are any number of pre-cut, ready-to-install solutions for sale or otherwise that may or may not solve your specific business...
16814
Daniel Sanchez Gonzalez
dsanchez@...
Jan 7, 2010 10:28 pm
Hello, We've a Project management process defined for covering PP and PMC. It includes WBS (task's effort size must be about 20 hours), estimation process,...
are you in mexico?¡ On Thu, Jan 7, 2010 at 10:29 AM, Daniel Sanchez Gonzalez < ... are you in mexico?¡ On Thu, Jan 7, 2010 at 10:29 AM, Daniel Sanchez...
Dear Dani, The short answer is yes. The CMMI does NOT prescribe any PM tool or level of tracking. These decisions are left up to the organization to make. ...
Often training is neglected in organizations. If people who manage projects are trained in the science and art of project management, these questions would not...
16818
Daniel Sanchez Gonzalez
dsanchez@...
Jan 8, 2010 1:36 pm
Victor, I'm from Spain. Thanks Henry. You're right, but some model interpretations are too restrictive. I've would like too hear some implementation...
One point to add to Christof's response. The focus of MA is to understand what measurements are useful and how they will be collected, analysed and stored. The...
Dani, Yes, absolutely! While the language in PP/PMC tends to be a bit "traditional" (something that will be addressed, at least a little, in v1.3) there is no...
And then back to the original question: "What is a measurement repository supposed to look like?" Hello again, GS - The term 'measurement repository39; is a...
Indeed there is no standard for a measurement repository but maybe it is time to have one - it would accelerate the process of implementation and facilitate...
I have a little services question for services-qualified people on the forum Lets suppose that there is a finance/cost accounting group of 10 people that have...
Rad A standard measurement repository would imply standard needs, products, and uses While I see the same measures in most measurement systems, they are...
Neil, If one uses the definition of "project" in the SVC context (or even if you do not): PP and PMC are going to be the annual budget planning and tracking...
Hi Neil, Interesting question. So, it can be clear that the customer with whom the organization has a service agreement would be the developers. But are they?...
hi Ed / Hillel, Bruce thanks for the clarifications. I agree with all. My take is, for a small group that provides a continual service that does not change,...
Hi Neil, Yes, PP/PMC are most easily discernible in services contexts when the service organization must affect a 'project39; to take on something out of the ...
Hello, I am a newbie at this site. I am interested in applying CMMI techniques to modeling and simulation efforts. I do not mean the modeling and simulation of...
Hi Len, Your work may benefit from many of the goals and practices in CMMI for Services. It's also likely that you may benefit most from taking a continuous,...
Hi Len, In my experience, a pure R&D shop has difficulty implementing the CMMI-DEV because of the free form nature of the environment and work. However, what ...
Hi Len  I agree that requirement related documents may not be required but defeinitely the Design (Technical Solutions), Testing (Verification & Validation),...
Hi In our org measurement repository consists of: 1. Project related metrices (Efforts / Sch Var, Productivity, Defect Closure Time, Review Efficiency, Defect...
We're really sorry for the short notice, but we've finally worked out the location for this seminar: APLN-MD/GB SPiN will be presenting a *low-cost seminar* on...
Parag Not sure what you are asking. OID can involve the use of PPMs, but as a process area, there are no requirements or expectations that there are PPMs for...