Search the web
Sign In
New User? Sign Up
cmmi_process_improvement · CMMi Process Improvement
? Already a member? Sign in to Yahoo!

Yahoo! Groups Tips

Did you know...
Real people. Real stories. See how Yahoo! Groups impacts members worldwide.

Best of Y! Groups

   Check them out and nominate your group.
Having problems with message search? Fill out this form to ensure your group is one of the first to be migrated to the new message search system.

Messages

  Messages Help
Advanced
Messages 6560 - 6589 of 16672   Oldest  |  < Older  |  Newer >  |  Newest
Messages: Simplify | Expand   (Group by Topic) Author Sort by Date ^
6560
Definitions I know are: Failure: observed erroneous behaviour, e.g. system crashes Fault: underlying cause in the product, e.g. buffer overflow Error: the...
Andre Heijstek
andreheijstek
Offline Send Email
Jul 1, 2006
8:19 am
6561
We are in search of good speakers on Software Estimation for an internal quality meet. It would be great if you can suggest some names in India. Pradeep C ... ...
Baba
cpradeep695
Offline Send Email
Jul 2, 2006
3:19 am
6562
Hello Prem, try this link: http://www.sqi.gu.edu.au/cmmi/report/ Best regards, Luigi Buglione, Ph.D. http://www.geocities.com/lbu_measure/ ...
Buglione Luigi
lbu_measure
Offline Send Email
Jul 2, 2006
3:20 am
6563
Hello, hoping it's not too late, here my two cents on this issue. First of all, when speaking about "productivity", please take care about which side of...
lbu_measure
Offline Send Email
Jul 2, 2006
3:20 am
6564
Dear Pat, our consultant is saying that insted of having different size for different product component(Mechanical,Hardware,Softwre)we shall have one comman...
vibhanshu bhardwaj
vibhanshu2
Offline Send Email
Jul 2, 2006
3:26 am
6565
Vibhanshu, You should use consultant's advice just like you do any other tool - use it where it makes sense and use something else when it doesn't! There is...
Patrick OToole
pactotoole
Offline Send Email
Jul 2, 2006
2:45 pm
6566
Dear Vibhanshu, I would suggest you the same thing what Pat has already suggested. I was working for an organization where we had same problem and after 2-3...
Hariprakash Agrawal
ahariprakash
Offline Send Email
Jul 2, 2006
2:45 pm
6567
Vibhanshu, WHY is the consultant recommending a single size metric? Is there some underlying problem that s/he is trying to solve, or is it a mistaken belief...
Patrick OToole
pactotoole
Offline Send Email
Jul 3, 2006
2:00 am
6568
Hi, Pat's views are correct. They are practical, realistic, and meaningful. However, consultants often give readymade solutions that does more harm than good....
Rajendra Gupta
gupta.rajendra
Offline Send Email
Jul 3, 2006
2:00 am
6569
Vibhanshu Along with pat's comments, I would ask the consultant why he/she thinks everyone needs the same size metric. Do they have some rationale? If this...
Neil Potter
neilspotter
Offline Send Email
Jul 3, 2006
2:00 am
6570
Hello, I am not the consultant recommending a single size metric, and I am not a LA (Lead Appriaser) yet! (But planning to become one in the near future) I can...
Orhan KALAYCI
orhankalayci...
Offline Send Email
Jul 3, 2006
4:21 pm
6571
Considering a CMMi Lvl2 Class A appraisal, if all practices (125) are Partially Implemented ( = no direct artifact present but artifacts or affirmations...
anthony desert
anthonydesert
Offline Send Email
Jul 3, 2006
4:26 pm
6572
Hello friends, Ashish, Anitha Good Morning!! My understanding of the error/defect goes something like this: If we unearth any non conformance in a particular...
Mahal N Sridhar
mnsiddi
Offline Send Email
Jul 3, 2006
4:44 pm
6573
Thanks a million... Cheers Prem Buglione Luigi <luigi.buglione@...> wrote: Hello Prem, try this link: http://www.sqi.gu.edu.au/cmmi/report/ Best...
Premkumar Jagatheesan
premkumar_mj
Offline Send Email
Jul 3, 2006
4:45 pm
6574
Dear Luigi Buglione, i am not able to open the link provided in the mail please help me. Vibhanshu ... === message truncated === ...
vibhanshu bhardwaj
vibhanshu2
Offline Send Email
Jul 3, 2006
4:45 pm
6575
Hi Baba, according to NQA, a major non conformity (NC) is is one that has a direct effect on the quality system or the product or service, while a minor one is...
Buglione Luigi
lbu_measure
Offline Send Email
Jul 3, 2006
4:54 pm
6576
Anthony, Yes, if all practices are "Partially Implemented" a lead appraiser can certainly conduct an appraisal, but no goals will be satisfied. In order for a...
Patrick OToole
pactotoole
Offline Send Email
Jul 3, 2006
6:19 pm
6577
I would use a much simpler definition. If you had to change/correct it then it was a defect. There are reviews that occur within a phase that would cause...
Hillelsohn, Michael
MHillelsohn@...
Send Email
Jul 3, 2006
6:19 pm
6578
Hi Anthony Your usage of the FI, PI and LI terms convey the idea that you have read through the MDD v 1.1 or that you have attended the SCAMPI Team training To...
Mathi Ezhil Arasu
chowtoh2000
Offline Send Email
Jul 4, 2006
2:40 am
6579
Orhan, Actually, in the original post, Vibhanshu indicated that they create 5 different types of components: "(Mechanical,Hardware,High Level Software,Embeded...
Patrick OToole
pactotoole
Offline Send Email
Jul 4, 2006
2:41 am
6580
I just wana Add my question in this context. If one company have got ,let say ,4 projects BEFORE the Class C appraisal and after Class C ,appraisal many gapes...
Muhammad Ali Inayat
abacmmi
Offline Send Email
Jul 4, 2006
1:39 pm
6581
Is there anyone who can explain following acceptance criteria of requirements with example ... Irfan Ali Noor...
irfanali_noor
Offline Send Email
Jul 4, 2006
1:40 pm
6582
Vibhanshu, here is the PSU webpage link: http://www.geocities.com/lbu_measure/psu/psu.htm <http://www.geocities.com/lbu_measure/psu/psu.htm> (it remained a dot...
Buglione Luigi
lbu_measure
Offline Send Email
Jul 4, 2006
1:41 pm
6583
Hello Pat, There is no disagreement between you and me, I totally agree with you. I said if they use "the same" process then they need one size metric ...
Orhan KALAYCI
orhankalayci...
Offline Send Email
Jul 4, 2006
1:50 pm
6584
Hi Friends, My understanding is that an error is something that may or may not cause a fault. Eg: Spelling error. But if that spelling was to be used to write...
Anitha Pai
anithaprao
Offline Send Email
Jul 4, 2006
1:58 pm
6585
OK thanks. In other words, at CMMi L2 all the 125 practices shall be at least "Largely Implemented" if the company want to be certified. It implies that each...
anthony desert
anthonydesert
Offline Send Email
Jul 4, 2006
2:26 pm
6586
Anthony, Yes, in order for a practice to be characterized as "Fully Implemented" or "Largely Implemented" at the instantiation level (e.g., effort estimation...
Patrick OToole
pactotoole
Offline Send Email
Jul 4, 2006
4:37 pm
6587
Well, I am not very sure about the total number of Practices for the Level 2 Process Areas If you have arrived at 125 practices – by adding up the 10 GPs for...
Mathi Ezhil Arasu
chowtoh2000
Offline Send Email
Jul 4, 2006
4:42 pm
6588
Irfan, Perhaps this is best illustrated with the kinds of remarks that you'd hear from the customer when the criteria is NOT met: Clear and properly stated -...
Patrick OToole
pactotoole
Offline Send Email
Jul 4, 2006
4:44 pm
6589
Muhammad, The purpose of an appraisal is to determine the organizational strengths and weaknesses compared to a model or standard. If the organization...
Patrick OToole
pactotoole
Offline Send Email
Jul 4, 2006
4:46 pm
Messages 6560 - 6589 of 16672   Oldest  |  < Older  |  Newer >  |  Newest
Advanced
Add to My Yahoo!      XML What's This?

Copyright © 2009 Yahoo! Inc. All rights reserved.
Privacy Policy - Terms of Service - Guidelines - Help