Lee: Great reply! Do you know if an FMEA analysis has been done on executive pay at banking or financial institutions? Thanks, Rodolfo Padron Tampa, Florida ...
That would be an interesting correlation wouldn't it _____ From: fmeainfo@yahoogroups.com [mailto:fmeainfo@yahoogroups.com] On Behalf Of Rody830@... Sent:...
I need guidelines on to prepare FMEA for Die design or sample FMEA on Die design ( Casting/ injection moulds etc., )...
656
Dev Raheja
raheja@...
Dec 29, 2008 9:18 pm
I can offer the guideline below. If you want generic FMEA procedure, you may buy my book "Assurance Technologies Principles and Practices (Wiley 2006) The...
Dear All, I am contacted by a engineering group to help them with the design of a car based on solarenergy to attend the race in Australia later this year. Is...
I will volunteer to help. _____ From: fmeainfo@yahoogroups.com [mailto:fmeainfo@yahoogroups.com] On Behalf Of Eric Sent: Friday, March 13, 2009 1:54 PM To:...
Hi Robert, Really interesting construct a concept fmea over a car solar energy I think that this is the begining a new age¡¡¡¡ Regards, José ... From:...
Dear all, I'am a student in one of university in Indonesian and now I am doing research in design hospital equipment using FMEA based fuzzy utility cost...
Robert, FMEA is basically to identify the potential trouble shooters identified by High RPN. Previously there was a ceiling in the RPN up to 1000. But recent...
Hello all of you, I'm new in this community I use FMEA to upgrade the maintenance scheme of our plant. 'Take a lot of time. I wondered if anybody already found...
664
Dev Raheja
raheja@...
Apr 23, 2009 5:54 am
If you have interest in learning fMEA for sped and efficiency, you may want to attend my SAE course on June 15-16. The title is "Design for Reliability,...
Hi I'm an FMEA Consultant, yesterday I ran a one day overview, one of the attendees was a Maintenance Development Manager, he also had used the approach you...
666
Dev Raheja
raheja@...
Apr 24, 2009 1:21 pm
I did FMEA in one day with Nissan. They left out all the bullshit about Severity, Frequency, and Detection ranking. Engineering Manager participated as a team...
I think your breakdown into technology blocks is a good idea. Many times you will use a motor many times and if you are making motors, having them analyzed at...
Hi, the question is if typically also inspection steps during production (measuring, inspection, final tests) are covered by a process FMEA or if it is only...
Dear all, I'am a student in one of university in Indonesian and now I am doing research in design hospital equipment using FMEA based fuzzy utility cost...
Inspection is always covered in a process FMEA, just not as a process step. The proces controls columns (Prevention and Detection)allow for an analysis of the...
Hi I am looking for FMEA application in Learning Management process with respect to Telecom (enterprise services) company. Can you please help me with some...
Dear all, I want to perform a FMECA for a safety analysis (nuclear facility). I am looking for some specific approaches, notably to define Frequency, severety,...
We found this interesting question in our FMEA mailbox. Hope someone can help this guy and his Solar Team. In case you can help him put him in cc of your mail:...
Hello, Can anyone advise on what criteria are used to identify the following Special Characteristics in a DFMEA and PFMEA, in terms of Severity, Occurrence and...
Hi all, I am ramping into FMEA, and currently use AGILE methodology for software development. We are looking to adapt FMEA to software, and to Agile methods....
Hi, You may like to have a separate worksheet for FMEA pertaining to each phase of sixsigma implementation. But it would be appropriate to use a tool which can...
Hi folks, I am facing a task of doing a risk analysis in computer networking department environment based on the FMEA method. As long as the analysis should be...
1)Start at system with a boundary diagram (all components of the system inside the boundary and all external interfaces to the outside and a list of Noises...
681
Robert Cassidy
rcassidy@...
Jul 7, 2011 12:56 pm
Hello Bob, I would start with an Ishikawa Diagram (cause and effect) on your "heterogeneous environment". This will become quite complex based on your...
Hi folks, I am facing a task of doing a risk analysis in computer networking department environment based on the FMEA method. As long as the analysis should be...