Yeah, I think I just need to do some controlled experiments, copying a project to a target, changing in the target and doing compares until I understand the...
Before you compare the project, delete the cache and just make sure that the upgrade tab is checked. If the object is locked in target env. by some other...
I would agree this may work in some cases but we were starting with a clean environment on a go live, so cache is not always the only issue. It is always good...
I'm looking at the record layout for subrecord CF7A_AK_SBR (Financials 8.8), and when I display the keys, it shows "Not" in the Key column for the last four...
Greg Coles
Greg.Coles@...
Jan 2, 2008 5:27 pm
48098
... the objects will not get migrated. << Does this also mean that if an end-user is accessing this page thru the PIA, it won't get migrated, or only if the...
At our installation we are modifying PS-Delivered pages, components and page/component peoplecode all with just cosmetic changes. We do it first in TST and...
Are those same fields marked as unused chartfields in the chartfield configuration? I *seem* to recall that it has something to do with that, but it's been a...
All, I do not fully understand how and when PPV (Transaction Group 400) gets posted to the GL. I do know that we are having major issues with PO_PRICE being 0...
What questions do you have? I don't have a lot of extra time but if you have something in particular then please narrow down your question or else I would ...
Hi, I am facing a tricky challenge. I am designing a custom timecard, and am trying to figure out how to implement a requirement for some dropdowns (prompt...
Only if the object in the target environment is LOCKED using the PeopleTools change control locking mechanism. If a developer has that object open, but NOT...
We are using just starting to use PI and are already questioning the data being pumped out - is the baseline a static row? That is, does the baseline change...
Yes, they are unused chartfields. Thanks for the input. That explains it. Greg ... Are those same fields marked as unused chartfields in the chartfield ...
Greg Coles
Greg.Coles@...
Jan 3, 2008 6:35 pm
48109
We are starting work on a project to change our project IDs. We currently use five characters of the field and we are changing it to eight. All tables with...
Greg Coles
Greg.Coles@...
Jan 3, 2008 6:54 pm
48110
Greg, I will give my opinion, although it is a character field leading with a zero is not a good idea at least in my opinion. Can allow for some programming...
Has anyone performed a delete process in PI? Trying to talk a client out of doing this - I know links and shadow tables could present issues (are all records...
Are you just trying to delete for a particular run ID? We delete from the PI tables, particularly when we're testing changes but also when we archive the...
To summarize what I think you are asking is: How do you setup a prompt on a page (meaning what happens when you click on the magnifying glass) to use a key...
Thanks for repllying Linda - we are on the PSPI/ADP Connector version . We want to delete down to the baseline and are leary of any haning 'chads' in tables...
Note, as delivered, the Project ID is 15-digit alpha/numeric (character field), is auto-numbered, and defaults with leading zeros (e.g. 000000000000001). This...
Greg, I agree with Tom and Mitch about the Leading zero. You may want to play it safe by having a character/number other than zero. To answer your original...
Hi J9, What version of FSCM are you on and what patch level? What kind of POs are you seeing this with - service types with no receipt required or physical...
It's all very convoluted but after sitting with the user's and testing the receivers with issues, we found that the problem lay with the POs themselves. The...
Sorry but I'm not familiar with the ADP Connector version. We have regular Payroll Interface and I have no idea if it's similar to what you have. ... From:...
The proper thing to do create a new baseline before you archive/purge the data. You create a new baseline by running the Export process and selecting the Full...