Need Expert Help for Preparing Schedule of Jetty Projects   Message List  
Reply | Forward Message #88 of 105 |
Hello Everyone,
Currently I am preparing Schedule in Primavera for L3 Level for Jetty & Backup Yard  (Port) Projects............Need some expert comment who had work on Jetty(Port Projects) Projects using Primavera or MSP................
While creating WBS I want to know that how the other organization is creating WBS.
 
e.g. I had two option with me for WBS....
 
Phase (Engineering, Procurement, Contracts, Construction) -----Main WBS
 
Now question is for Construction which option is best or any other suggetion: 1st Option is
COMMON
         DREDGING
         ASSESSORIES
         RETAINING WALL
GANTRY 1
         PILING
         HEADSTOCK
         PRECAST PLANK
         DECK CASTING 
GANTRY 2
         PILING
         HEADSTOCK
         PRECAST PLANK
         DECK CASTING
GANTRY 3
         PILING
         HEADSTOCK
         PRECAST PLANK
         DECK CASTING
GANTRY 4
        PILING
        HEADSTOCK
        PRECAST PLANK
        DECK CASTING
 
Second Option 2:
 
COMMON
         DREDGING
         ASSESSORIES
         RETAINING WALL
BENT 1
        GANTRY 1
                  PILING
        HEADSTOCK
        PRECAST PLANK
        DECK CASTING
 
BENT 2....etc....(Total no of Bent is 100)
 
now my problem is..........if i m taking option 1 Headstock & Precast Plank & Deck Casting are done for the Bent wise not by Gantry wise.......
 
If i choosing option 2.....
 
Bent number are too many also Precast Plank are between Bent & it had been divided into no of Grid.....
 
Bit confused which common strategy to use for all the Ports Projects there are 4 Jetty Projects with Backup Yard.
 
If anyone had work with this type of Projects Please help...........
 
Thanks & Regards,
 
Jay Pancholi


JAY V. PANCHOLI [M.Tech(C.P.M), B.E. Civil]
8,DAXINI SOCIETY,MANINAGAR,
Nr. Bus-Stand, AHMEDABAD- 380 008.
GUJARAT,INDIA.
PH. NO. 091-079-25468940
(R)
             091-080-26017172 (O)


                                               


Yahoo! Messenger with Voice. Make PC-to-Phone Calls to the US (and 30+ countries) for 2¢/min or less.

Thu Mar 23, 2006 12:17 pm

pancholijay
Offline Offline
Send Email Send Email

Forward
Message #88 of 105 |
Expand Messages Author Sort by Date

Hello Everyone, Currently I am preparing Schedule in Primavera for L3 Level for Jetty & Backup Yard (Port) Projects............Need some expert comment who...
Jay Pancholi
pancholijay
Offline Send Email
Mar 23, 2006
12:18 pm