Rama, The only thing I can add to most of the responses already given is that you can tell your mgmt that your velocity reflects the truth. The team's ...
55062
Charles Bradley - Scr...
charles_brad...
May 8, 2012 10:18 pm
+1 to Mark W's answer below. Â ... Charles Bradley http://www.ScrumCrazy.com ... +1 to Mark W's answer below. ------- Charles Bradley...
55061
Steve Ropa
steveropa
May 8, 2012 10:16 pm
Don't forget to follow it up with Clean Coders. The two books together should be required reading for anyone who wants to practice the craft of programming. ...
55060
Steve Ropa
steveropa
May 8, 2012 10:14 pm
Agreed. I like to point out that we are estimating how big this story is without regard as to who may or may not end up working on it. I would much rather...
55059
extremeprogrammer
extremeprogr...
May 8, 2012 9:01 pm
The rolling average may be a good idea, because there will always be variation in velocity from sprint to sprint and it can help with longer term planning. ...
55058
George Dinwiddie
gdinwiddie
May 8, 2012 8:55 pm
Simon ... Could it be a sign of too much Work In Progress? I discuss shapes of burndown charts in my Better Software article, ...
55057
David H
sebi13556
May 8, 2012 7:08 pm
I like ranges. Working with ranges rather than absolute numbers or medians is so much nicer. Try ranges, they work. -d...
55056
woynam
May 8, 2012 7:06 pm
No, that is not correct. The velocity for Sprint 1 will not include the unfinished stories. Thus, the full size of the stories will be part of the velocity...
55055
gopinath
gopinath_ram
May 8, 2012 6:49 pm
I am in agreement with previous responses to this question. However at the beginning of Sprint 2 you should re-estimate the story points for the two partially...
55054
Wouter Lagerweij
wouterla
May 8, 2012 6:00 pm
Hi Jeff, What you describe seems to be 'textbook39;, in that it's exactly as it was put in the scrum guide, and many scrum books. No problems there. What I...
55053
gregc
graycole
May 8, 2012 5:45 pm
Yves, On the off chance you will be at the SQE Better Software Conference West, I'll be presenting some strategies to use. But I prefer to use multiple lenses...
55052
vercinget_xx
May 8, 2012 4:37 pm
16. People subtly (and sometimes not so subtly) pressured to lie about the "real" status, so as not to bring down the wrath of the higher-ups. I cannot count...
55051
vercinget_xx
May 8, 2012 4:31 pm
When I first looked at the graph, I thought your actuals were actually *too* close to the ideal. The line *should* actually go up before it goes down, because...
55050
extremeprogrammer
extremeprogr...
May 8, 2012 4:27 pm
Hi. Your first two paragraphs seem to suggest that you've completed 5 stories in each of the first two sprints, but your third and fourth paragraph suggest...
55049
Laurent Bossavit
morendilfoo
May 8, 2012 4:26 pm
... The way that backfired in this instance could serve as a textbook example of "chilling effect". :)...
55048
Steve
steveatootac
May 8, 2012 3:55 pm
I'm with Kurt Stop discussing how long something will take and start thinking about the 'size and complexity39; Your first round voting will show up differences...
55047
Wouter Lagerweij
wouterla
May 8, 2012 3:46 pm
Hi Simon, The ideal line is not very useful, but not finishing anything for the first week would worry me. And it also seems that after not finishing the first...
55046
Steve
steveatootac
May 8, 2012 3:44 pm
Simon - if it isn't a problem, why change anything? Scrum is about delivering business value not having pretty charts! I personally do not use a Sprint...
55045
Steve
steveatootac
May 8, 2012 3:39 pm
Hi Yves I have never done as yo suggest because it is much easier for the PO business to take 2 PBI and say which is more important than the other. Keep doing...
55044
Steve
steveatootac
May 8, 2012 3:33 pm
Hi Rama How do you know that Sprint 2 has 50 points? You shouldn't be planning Sprint 2 until Sprint 1 has finished! You take the velocity achieved in Sprint...
55043
Steve
steveatootac
May 8, 2012 3:26 pm
Ram - forgive me, are you being serious? Project Status is the results of the Sprint/Release review. Yes you can document it and send to others who couldn't be...
55042
Mark Levison
marklevison
May 8, 2012 3:16 pm
I replied on Google+. Burndown Charts lie. I generally recommend to my clients that they don't use them. Please help us by showing snapshots of your story...
55041
Steve
steveatootac
May 8, 2012 3:11 pm
Hi A 'problem39; with Scrum is that it starts with a Product Backlog; it would then suggest that you cannot do Scrum if you cannot get a PB! However, may I...
55040
Bret Wortman
WortmanB
May 8, 2012 3:10 pm
Ignore the ideal line -- it's a marketing tool created by the software tools because some customer demanded it. Ignore it, or demand that your software tool...
55039
Mark Levison
marklevison
May 8, 2012 3:08 pm
In addition I use a trailing average over three sprints to smooth out normally variance. Remember velocity has only two uses: - Give a rough guide as to how...
55038
woynam
May 8, 2012 3:01 pm
Wait. Let me take a stab at answering my own question. Green: The product backlog is growing. As we deliver valuable features to our users, they're excited by...
55037
Alan Dayley
alandond
May 8, 2012 2:43 pm
+1 to Paul's answer. Alan...
55036
woynam
May 8, 2012 2:41 pm
What on earth would red, orange, and green represent? Mark...
55035
Steve Ropa
steveropa
May 8, 2012 2:01 pm
+1 This is a very normal burndown. I for one hate the ideal line, as I've seen too many teams chase this phantasm. This leads them to want to do the...
55034
Kurt Häusler
kurt.haeusler
May 8, 2012 1:58 pm
What do you use the "business value" value for? I usually find it very difficult to estimate the business value of a single story, so I don't bother. In fact...