Hello Promod,
I am reproducing Bangalore SPIN benchmarks for LC phases
mentioned by you:
Requirements analysis: 8%
Design: 15%
Development: 44%
Testing: 19%
Also, Proj. Mgt. effort is about 10% and others (CM,
Training, SQA e.t.c.) 4%.
These are the AVERAGES and actuals slightly very, depending upon
the technology, domain and size of the project. For a 100 FP size project, the
headcount will be about 100 person days.
I can share the Bangalore SPIN benchmarks with you and other members,
if required.
Best Regards,
Ribhu
From: spi@yahoogroups.com
[mailto:spi@yahoogroups.com] On Behalf Of pramod_p1
Sent: 02 October 2008 14:38
To: spi@yahoogroups.com
Subject: [SPI] Head Count and Time Lines for a typical s/w project in
Telecom industry .
Hello All,
Currently I am conducting a survey as a part of my paper
presentation. The topic is resource utilisation for IT development
across multiple industries. i.e. telecom, retail, utility.
I request your help for completing this.
I am looking some data on:
What will be the head count for each phase of a typical project of
100 function points (fp) or projects of similar size in Telecom ?
i.e. Requirement Analysis, Design, Development, Testing (all
stages).
What is the time line for each phase?
Can any one help me by providing data or tell me where I can find
these data?
Many thanks
in advance
Regards,